Identifying risk factors of the modular integrated construction (MiC) project in its assembly stage

Hồ Lê Nguyên , Đỗ Tiến Sỹ Đỗ Tiến Sỹ , Nguyễn Thanh Việt

Abstract

In the context of increasing adoption of Modular Construction (MiC) in Vietnam to reduce costs, accelerate timelines, improve project quality, and integrate with the growing and developing Construction 4.0 industry in Vietnam, effectively managing and implementing successful MiC construction projects requires efficient handling of risk factors. Based on the comprehensive results of worldwide articles, data analysis from 158 survey forms, along with direct interviews with 12 experienced experts with 10-25 years of experience in MiC construction, the data analysis identified 35 factors influencing the implementation of MiC construction projects during the installation and construction phase. Furthermore, an analysis of causes and measures to address risks was conducted for the five most significant risk factors.

References

  1. Indochine Engineering, “Why modular construction? Process Typical modular structure construction phrases Typical modular structure assembling process.”
  2. M. Kamali and K. Hewage, “Life cycle performance of modular buildings: A critical review,” Renewable and Sustainable Energy Reviews, vol. 62. Elsevier Ltd, pp. 1171–1183, Sep. 01, 2016. doi: 10.1016/j.rser.2016.05.031.
  3. I. Y. Wuni, G. Q. Shen, and B.-G. Hwang, “Rủi ro khi xây dựng tích hợp mô-đun: Đánh giá và hướng nghiên cứu trong tương lai,” Front of Engineering and Management, 2019.
  4. H. N. Tuệ, “Dự báo tiến độ thi công công trình lắp ghép bằng trí tuệ nhân tạo,” Trường Đại học Bách Khoa, ĐHQG-HCM , 2018.
  5. L. V. Thông and T. K. Tường, “Nhà lắp ghép và các yêu cầu để phát triển tại Việt Nam,” Tập san UAH, 2019, [Online]. Available: http://www.uah.edu.vn
  6. P. V. H. Sơn and H. T. Hiếu, “Phát triển thuật toán lai ghép kiến sư tử (ALO) để tối ưu chi phí logistíc cho cấu kiện bê tông đúc sẵn,” Tạp chí khoa học công nghệ xây dựng, ĐHXDHN, vol. 16, no. 1V, pp. 48–63, 2021, doi: 10.31814/stce.huce(nuce)2022-16(1V)-05.
  7. N. H. Hà and N. T. Giang, “Đánh giá kỹ thuật về nhà ở lắp ghép do công ty Vinaconex Xuân Mai thiết kế và thi công,” Viện KHCN Xây dựng.
  8. A. A. Khan, R. Yu, T. Liu, S. Sepasgozar, and C. Chen, “A Systematic Review of Risks in Modular Integrated Construction Practice.” [Online]. Available: https://www.researchgate.net/publication/356160962
  9. I. Y. Wuni, G. Q. Shen, and B.-G. Hwang, “Risks of modular integrated construction: A review and future research directions,” Frontiers of Engineering Management, vol. 7, no. 1, pp. 63–80, Mar. 2020, doi: 10.1007/s42524-019-0059-7.
  10. I. Y. Wuni and G. Q. P. Shen, “Risks Identification and Allocation in the Supply Chain of Modular Integrated Construction (MiC).”
  11. C. Z. Li, G. Q. Shen, F. Xue, L. Luo, X. Xu, and L. Sommer, “Schedule risk modeling in prefabrication housing production,” J Clean Prod, vol. 153, pp. 692–706, Jun. 2017, doi: 10.1016/j.jclepro.2016.11.028.
  12. H. Xian Li, M. Al-Hussein, Z. Lei, and Z. Ajweh Hong Xian Li, “Risk identification and assessment of modular construction utilizing fuzzy analytic hierarchy process (AHP) and simulation.” [Online]. Available: www.nrcresearchpress.com
  13. I. Y. Wuni, G. Q. P. Shen, and A. T. Mahmud, “Critical risk factors in the application of modular integrated construction: a systematic review,” International Journal of Construction Management, vol. 22, no. 2, pp. 133–147, 2019, doi: 10.1080/15623599.2019.1613212.
  14. I. Y. Wuni, G. Q. Shen, R. Osei-Kyei, and S. Agyeman-Yeboah, “Modelling the critical risk factors for modular integrated construction projects,” International Journal of Construction Management, vol. 22, no. 11, pp. 2013–2026, 2020, doi: 10.1080/15623599.2020.1763049.
  15. J. S. Lee and Y. S. Kim, “Analysis of cost-increasing risk factors in modular construction in Korea using FMEA,” KSCE Journal of Civil Engineering, vol. 21, no. 6, pp. 1999–2010, Sep. 2017, doi: 10.1007/s12205-016-0194-1.
  16. S. G. Brissi, L. Debs, and E. Elwakil, “A review on the factors affecting the use of offsite construction in multifamily housing in the united states,” Buildings, vol. 11, no. 1. MDPI AG, pp. 1–23, Jan. 01, 2021. doi: 10.3390/buildings11010005.
  17. H. Trọng and C. N. M. Ngọc, Phân Tích Dữ Liệu Nghiên Cứu Với SPSS. NXB Thống Kê, 2005.